September 20265 min readBy Oraya Builders Team
How to Pay Your Contractor Safely: Stage Payments Explained
Paying a large advance is the most common way homeowners lose money. Here is a safer way to pay for building work.

On this page
The Big Advance Problem
Many contractors ask for 30% to 50% of the money upfront. If the work slows down or the contractor disappears, you have already paid for work that was never done. Stage payments fix this.
What Are Stage Payments?
You pay in parts. Each part is paid only after a clear stage of work is finished and checked on site. For a grey structure, a simple schedule could be:
- Signing: a small mobilisation amount, so the team can set up on site.
- Foundations done: digging, termite spray and footings finished.
- Ground floor slab poured: columns, beams and the first roof complete.
- First floor slab poured: second level frame complete.
- Brickwork done: all walls built on both floors.
- Plaster and pipes done: walls plastered, electrical and plumbing pipes laid.
- Handover: final check, and the last payment.
Rules That Protect You
- Get it in writing. The contract should list each stage, the amount, and what "done" means for that stage.
- Check before you pay. Visit the site, or send an engineer you trust, before each payment.
- Fixed rates. Ask for a BOQ (cost breakdown) with a fixed rate for each item, so the price doesn't change halfway through.
- Keep a small amount back. Holding back a small part until a few months after handover gives the contractor a reason to fix any problems that show up.
- Late-delivery penalty. A good contract says what the contractor pays if they finish late without a valid reason.